Question:
Trophimus asks:
 

Is there a way to show who assigned/scheduled a work order in either assignment manager or work order tracking modules?  I need to see only the work orders assigned by me (Planner) in order to measure schedule compliance.

Projetech Maximo Expert Team answers: 

The ‘ASSIGNMENT’ table does not have a ENTERBY or CHANGEBY field, so your best bet to get this done easily, and without an add on, is to turn on electronic audit for the ‘ASSIGNMENT’ object/table, and the ASSIGNMENT.STATUS field. That way, when the status is updated, the user and date/time will be copied to the table/object ‘E_ASSIGNMENT’ assuming you use the default.

There are other options, but most involve dollars; this solution just involves a change in Maximo settings and a little downtime.

As long as you are v5 or higher, E-Audit is included; v4 customers would have needed the 21CFR Part 11 add on for electronic audit/signature.


View Archived Ask the Maximo Expert Q&As
 





 





           Authorized IBM Training



|
..
Home..|..Contact Us..|.. © 2010 Projetech Inc. All rights reserved..



Share/Bookmark


Follow Us:
  























Free Maximo upgrades
FREE MAXIMO
UPGRADE

Click
Maximo as a service
 Maximo Hosted
 from
 $595/month
 
Maximo mobile

Maximo Mobile Device


Projetech
Maximo
Mobile
Options
Maximo online training

Maximo Online Training

Self Paced Online
Instructor Led Online
View Free Demo!